Implementing Big Changes for the Commuting Public

A milestone has been reached: a traffic shift onto the newly-constructed Direct Connectors on the SH 288 Managed Lanes project. Since Monday, August 13th, the Direct Connectors taking drivers from IH-610 Eastbound to SH 288 Northbound, as well as from IH-610 Westbound to SH 288 Southbound has been open for the traveling public.

The opening of these new Connectors necessitates the demolition of the previously-driven Connector Ramps. As a result, on August 17, 2018, Almeda-Genoa Constructors implemented a series of total lane closures to support multifaceted construction efforts of Drive288, the SH 288 Managed Lanes Construction project.

All dates are subject to change and construction work could be postponed due to inclement weather.

 

CLOSURE #1:

All lanes of SH 288 Northbound and Southbound will be closed from Holly Hall St to IH 610. The mainlanes will be continuously closed on the following dates:

  • From Fri, 8/17/18 at 9pm – Sat, 8/18/18 at 12pm, Sun morning, 8/19/18 at 12am – Mon morning, 8/20/18 at 5am  
  • From Fri, 8/24/18 at 9pm – Mon morning, 8/27/18 at 5am  
  • From Fri, 9/7/18 at 9pm – Mon morning, 9/10/18 at 5am

CLOSURE #1 Detours: 

Northbound Traffic: Take SH 288 Northbound to IH 610 Eastbound. Exit Scott St and U-Turn to the IH 610 Westbound ramp. Take IH 610 Westbound to SH 288 Northbound.

Southbound Traffic: Take SH 288 Southbound to IH 610 Westbound. Exit Fannin St and U-Turn to the IH 610 Eastbound ramp. Take IH 610 Eastbound to SH 288 Southbound.

Click to Enlarge

Click to Enlarge

CLOSURE #2

All lanes of IH 610 Eastbound and Westbound will be closed from Scott St to Almeda Rd. The mainlanes will be continuously closed on the following dates:

  • From Fri, 8/17/18 at 9pm – Sat, 8/18/18 at 12pm, Sun morning, 8/19/18 at 12am – Mon morning, 8/20/18 at 5am  
  • From Fri, 8/24/18 at 9pm – Mon morning, 8/27/18 at 5am
  • From Fri, 9/7/18 at 9pm – Mon morning, 9/10/18 at 5am

CLOSURE #2 Detours: 

Eastbound Traffic: Take IH 610 Eastbound to SH 288 Southbound. Exit Bellfort Ave and U-Turn to the SH 288 Northbound ramp. Take SH 288 Northbound to IH 610 Eastbound.

Westbound Traffic: Take IH 610 Westbound to SH 288 Northbound. Exit Yellowstone and U-Turn to the SH 288 Southbound ramp. Take SH 288 Southbound to IH 610 Westbound.

Eastbound Detour Part 1

Click to Enlarge

Eastbound Detour Part 2

Click to Enlarge

Click to Enlarge

CLOSURE #3

The SH 288 Northbound direct connector to IH 610 Westbound will be closed. The mainlanes will be continuously closed on the following dates:

  • From Fri, 8/17/18 at 9pm – Sat, 8/18/18 at 12pm, Sun morning, 8/19/18 at 12am – Mon morning, 8/20/18 at 5am  
  • From Fri, 8/24/18 at 9pm – Mon morning, 8/27/18 at 5am  
  • From Fri, 9/7/18 at 9pm – Mon morning, 9/10/18 at 5am

CLOSURE #3 Detour: 

Click to Enlarge

Take SH 288 Northbound to IH 610 Eastbound. Exit Scott St and U-Turn to the IH 610 Westbound ramp.

CLOSURE #4

The SH 288 Southbound direct connector to IH 610 Eastbound will be closed. The mainlanes will be continuously closed on the following dates:

  • From Fri, 8/17/18 at 9pm – Sat, 8/18/18 at 12pm, Sun morning, 8/19/18 at 12am – Mon morning, 8/20/18 at 5am  
  • From Fri, 8/24/18 at 9pm – Mon morning, 8/27/18 at 5am  
  • From Fri, 9/7/18 at 9pm – Mon morning, 9/10/18 at 5am

CLOSURE #4 Detour: 

Take SH 288 Southbound to IH 610 Westbound. Exit Fannin St and U-Turn to the IH 610 Eastbound ramp.

Detour Part 1

Click to Enlarge

Detour Part 2

Click to Enlarge